Author Archives: mangelo

Moving Along!

Vance Brown is nearly complete with the building envelope. Exterior windows and doors have been installed and the plaster system is nearly complete with the …

View More

Big Things Happening…

The construction team continues working towards completion of the building envelope. The field crews are nearly complete with the metal roof system; completion expected in …

View More

Completion of the Building Envelope

The construction team is working towards another exciting milestone for the project: completion of the building envelope. The field crews completed roof paper and gutter …

View More

Topping-Out!

Nova Partners, Inc., Vance Brown, Inc., Hoover Associates, KRP Architects, and the San Francisco Design Center celebrated the Topping-Out of the Ronald McDonald House at …

View More

Team to be topped out in early August!

The construction team started construction of the roof framing in July. About 30 % of the roof structural framing members were installed and signed off …

View More

3rd Fl. Wall Framing has Commenced!

The construction team completed the wood floor joists installation for the third floor. The 3rd floor wall framing commenced and will continue through early July. …

View More

First and Second Floor Designer tour!

June – 2015 Under the design leadership of co-chairs Elizabeth Martin of Martin Group, and Geoffrey De Sousa of Geoffrey De Sousa Design and co-principal …

View More

First Floor Construction Complete!

April – 2015 The construction team completed the wood and steel framing of the first floor for the new expansion! The first floor includes the …

View More

Structural and Wood Framing

March 2015 – Vance Brown started and completed the structural and wood framing of the first floor of the new House! The team is now …

View More

Pour the Concrete!

February 2015 – Vance Brown completed the installation of the shoring system and reinforcing steel for the podium deck. Concrete for the first half of …

View More