08.14.2015
Team to be topped out in early August!

The construction team started construction of the roof framing in July. About 30 % of the roof structural framing members were installed and signed off …
View More
construction

08.14.2015
Team to be topped out in early August!

The construction team started construction of the roof framing in July. About 30 % of the roof structural framing members were installed and signed off …
View More
rm

07.16.2015
3rd Fl. Wall Framing has Commenced!

The construction team completed the wood floor joists installation for the third floor. The 3rd floor wall framing commenced and will continue through early July. …
View More
7

06.24.2015
First and Second Floor Designer tour!

June – 2015 Under the design leadership of co-chairs Elizabeth Martin of Martin Group, and Geoffrey De Sousa of Geoffrey De Sousa Design and co-principal …
View More
IMG_9450 (2)

04.15.2015
First Floor Construction Complete!

April – 2015 The construction team completed the wood and steel framing of the first floor for the new expansion! The first floor includes the …
View More