concrete

02.01.2015

Pour the Concrete!

February 2015 – Vance Brown completed the installation of the shoring system and reinforcing steel for the podium deck. Concrete for the first half of the podium deck was poured on February 12th. Concrete for the 2nd half of the podium deck was poured on February 26th. The next activities include removal of the garage structure formwork and installation of structural steel members and wood framing on the first floor. Steel and wood framing materials are due to arrive onsite the first week of March.